CLIENT

BT Energy for Darwin International Airport

YEAR COMPLETED

2022

SCOPE OF PROJECT

Eco Tech Electrical was engaged by BT Energy to carry out solar panel system installation at Wyuna Cold Stores. BT Energy provided the design, engineering, and procurement, and subcontracted onsite installation to Eco Tech Electrical. Works commenced in March 2021 with several delays due to long lead times in procuring materials during the pandemic. Installation and commissioning were completed in December 2022. The project was completed simultaneously with the Osgood Drive project.

KEY PERSONNEL

  • Adam Bate
  • David Rojas
  • Brady Bray